OpenAI's site announces the Grid Protectors Program. Future compute campuses are to reduce electricity demand when the grid is under strain, through arrangements with utilities, regulators, and policymakers. How much demand can be reduced, how quickly, and for how long will differ by location. Additional commitments are to be shared once they are finalized.

[1]
OpenAI wordmark in white on black
图片来源:OpenAI

For the planned Effingham County campus, the page says the project will pay the full infrastructure and electric-service costs required to serve it. The agreement with Georgia Power includes up to 1,000 megawatts of flexible demand response. The page's scale comparison is the average electricity demand of roughly 700,000 households, and it says the arrangement can free power for air conditioning during extreme heat. The campus is still in development. The page presents Effingham as a pilot for the program.

[1]

Georgia Power projects approximately $950 million in annual customer savings beginning in 2029 from its portfolio of large-load agreements and expected growth, including Project Camellia. It estimates a benefit of at least $15 a month for a typical residential customer using 1,000 kilowatt-hours. That is the utility's projection for a portfolio, not a bill already cut at Effingham alone.

[1]

The page also says flexibility cannot replace investment in new energy supply and transmission. A projection that U.S. data center capacity exceeds 100 gigawatts by 2030 is cited from an outside outlook, not measured by OpenAI on the page. Long-term contracts and financial assurances are described as protection for other customers if a project is delayed, reduced, or canceled. No operating date is given.

[1]